November 12, 2026
The Lake Harriet work this fall is on the road, at the north end, where traffic from Linden Hills and Lyndale Park meets the parkway. The 2027 work moves down to the water: the rest of the parkway pavement, then North Beach, then the stone wall along the western shore. The wall is the most expensive of these projects and the least settled. It is also the one most likely to change how the west-shore path looks after the work is done.
Taken in order, the projects tell you which part of the loop gets disrupted next, and roughly how much.
The Minneapolis Park and Recreation Board and the City of Minneapolis began work on Monday, Oct. 5, right after the Twin Cities Marathon. The plan covered three things: resurfacing Lake Harriet Parkway from W 42nd Street to Roseway Road, upgrading pedestrian ramps around the lake, and rebuilding the intersection with William Berry Parkway. Throughout the work, the bike and pedestrian trail on the north side stayed open, and so did the Bandshell south parking lot entrance at W 42nd Street.
The intersection is where the most will change. MPRB calls the current layout "atypical" and is replacing it with a standard T-intersection, raised crosswalks where the trails cross, and clearer sight lines. The stated goals are safer trail crossings, less driver confusion, and keeping the mature trees at the corner. The Park Board's survey of the design drew comments from both sides. Some respondents described sharp turns for cyclists and raised concerns about visibility, where the stop signs go, and conflicts between trail users. Others backed the new layout.
In its Nov. 6 construction update, MPRB said the concrete curb and gutter were in place. It expects lighting, trail upgrades and paving to be finished before Thanksgiving on Thursday, Nov. 26, and the roadway to open to traffic at that point.
The City's side of the project adds a detail that matters to bird watchers. On its Lake Harriet ADA ramp project page, the City lists four wildlife-friendly surmountable curbs between Roberts Bird Sanctuary and the wetlands on the north end of Lake Harriet.
The north segment was Phase 1 of the paving. MPRB's resurfacing page schedules the rest of Lake Harriet Parkway for Phase 2 in 2027. In other words, the road disruption you've seen at the north end this fall will reach other parts of the loop next year.
Two shoreline projects come next. Both draw on Met Council regional funding, and both deal with the spot where park infrastructure meets the water.
MPRB's beach improvements page lists 2027 as the anticipated construction timeframe for Lake Harriet North Beach and puts completion in spring to summer 2027. In August, MPRB staff told Southwest Voices the project would improve accessibility, replace aging infrastructure, meet life-safety requirements and handle needed maintenance. Retaining walls would provide structural support and protect the existing trees.
The Park Board's preferred concept from March 20, 2026 shows what the beach would include:
Southwest Voices also noted that the final scope will be "balanced to align with the budget," so the finished beach may not include every item on that list.
The biggest open question is on the western shore. The stone wall there was built by the Works Progress Administration. MPRB's shoreline repair page says large sections have worn down to the point of being unsafe and unstable. Some sections are missing stones, and others have shifted and lean toward the lake. As the wall degrades and the soil behind it erodes, the lake edge weakens, and so does the regional trail that runs on top of it.
The wall was built as stone veneer and a cap over a poured concrete core. A 2016 inspection found the faces and caps in uniformly poor condition, with the worst damage at the waterline. There, freeze-thaw cycles and moving ice wear down the masonry every winter. Where the inspectors could see the cores, they were sound.
MPRB lists the project as pre-design, with Phase 1 construction expected in 2027. It plans to spread the repairs over several years. The September open house was held on the shoreline near W 42nd Street, south of Bread & Pickle, so you can see the condition of the wall from there.
MPRB's wall repair options presentation prices four ways to rebuild the wall. Three of the four totals come with a footnote saying they don't include replacing the walking trail. The presentation estimates that work separately at $275,000 for 1,600 linear feet of 8-foot-wide trail with concrete ribbon curbs, including removal, materials and installation. The sheet pile total has no such footnote.
If you add the trail estimate where the footnote applies, the gap between options grows:
| Option | Wall estimate | With $275,000 trail estimate added where footnoted |
|---|---|---|
| Cast-in-place concrete | $1,299,700 | $1,574,700 |
| Geocells and riprap | $1,067,200 | $1,342,200 |
| Gabion baskets | $911,300 | $1,186,300 |
| Sheet pile | $824,000 | No footnote; $824,000 as presented |
The line items explain the difference. The concrete, gabion and geocell options each include $480,000 for temporary sheet pile and $80,000 for a dewatering system. In effect, each one first builds a temporary wall to hold back the lake and then builds the permanent wall behind it. The sheet pile option leaves out excavation, temporary sheeting and dewatering. It puts $640,000 into permanent sheet pile instead.
These are preliminary comparisons for an options review. Under the sheet pile approach, the shoreline would be rebuilt in steel, and the trail above it would not be priced for replacement. Under the other three, the trail is priced for full replacement, and the estimate is the same $275,000 in each case.
Once the north end reopens, winter on the lake runs on a simpler schedule. MPRB has closed restrooms at regional park facilities for the season, so walkers on Lake Harriet can't count on park restrooms until they reopen.
On the ice, Art Shanty Projects returns to frozen Lake Harriet, Bdé Umáŋ, from Jan. 16 to Feb. 7, 2027. The free program runs weekends from 10 a.m. to 4 p.m., with a suggested donation of $10 to $20, Southwest Voices reported. The shanties will sit on the same lake whose western wall has been damaged by ice at the waterline for decades.
Both shoreline projects have email updates you can sign up for on their MPRB pages. The shoreline repair page is where the selected wall option and the first repair stretch will appear. The beach improvements page covers North Beach alongside Lake Nokomis 50th Street Beach.
If you live near Lake Harriet and want to talk through how the shoreline and parkway work fits into your plans over the next couple of seasons, Aaron Spiteri follows these projects closely and is glad to talk. Let's Connect.
Stay up to date on the latest real estate trends.
Real estate has never been more competitive and in a market where every dollar matters, so does the professional you choose to represent you. You deserve more than an agent. You deserve a trusted and experienced advisor, a dedicated advocate, someone who understands the market, anticipates opportunities, and protects your interests at every stage of the process. My commitment is simple: to negotiate strategically, guide you with confidence, and fight tirelessly for every last dollar on your behalf. Whether buying or selling, I am committed to delivering an exceptional experience and the strongest possible result. Proudly ranked the #1 solo agent at Lakes Sotheby’s International Realty for total sales volume in 2025.